建築工事編成最適化システムの構築

Translated title of the contribution: OPTIMIZATION SYSTEM OF SUB-PACKAGE PROBLEM IN BUILDING CONSTRUCTION PROJECT USING MATHEMATICAL PROGRAMMING

則武 譲二, 古阪 秀三, 藤澤 克樹, 金多 隆

Research output: Contribution to journalArticle

Abstract

This paper describes the sub-package problem in the building construction project which is defined to combine various resources under some constrained conditions and multipurpose. Multipurpose includes the term of works, the cost, the quality, the safety, and so on. Various resources include the labor, the material, and the temporary facilities and machinery, etc. The sub-package is currently arranged through the personal judgment of the site manager. However, this way of arrangement comes to the limitation. In this paper, the methods of the sub-package in construction firms are collected through interviews and surveys. Then, the decision-making support system of the sub-package is developed to achieve the optimization with mathematical programming model where the evaluation criteria are the overhead cost and the management time in sub-package problem.
Translated title of the contributionOPTIMIZATION SYSTEM OF SUB-PACKAGE PROBLEM IN BUILDING CONSTRUCTION PROJECT USING MATHEMATICAL PROGRAMMING
Original languageJapanese
Pages (from-to)235-242
Number of pages8
Journal日本建築学会計画系論文集
Volume66
Issue number550
DOIs
Publication statusPublished - 2001